Multiple Choice
The ________ time for an activity represents low-cost, realistic, efficient methods for completing the activity under typical conditions.
A) normal
B) crash
C) estimated
D) accelerated
E) completion
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q50: The less steep the cost slope of
Q51: Creation of the _ graph keeps the
Q52: When crashing a schedule, this may set
Q53: As a project's duration is reduced, indirect
Q54: The cost-time crashing method relies on choosing
Q56: There are more options available for reducing
Q57: In a Project Cost-Duration Graph, total project
Q58: _ is the first thing to consider
Q59: As a project is crashed and project
Q60: The _ project cost is the sum