The less steep the cost slope of an activity, the
A) less it costs to shorten one time period.
B) more it costs to shorten one time period.
C) smaller the crash time is.
D) larger the crash time is.
E) cannot be determined by the information given.
Correct Answer:

Verified
Correct Answer:
Verified