Multiple Choice
A test engineer is to conduct environmental testing but the chamber cannot hold all the equipment that needs to be tested. This is an example of a constraint that could impact the sequence and timing of activities in a project network. What type of constraint is it?
A) Physical
B) Technical
C) Resource
D) Scheduling
E) Time
Correct Answer:

Verified
Correct Answer:
Verified