Multiple Choice
Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume the project starts on Monday, May 4, 2020 and no work is done on weekends (Saturday and Sunday) .
A) Monday, May 11, 2020
B) Saturday, May 9, 2020
C) Sunday, May 10, 2020
D) Tuesday, May 12, 2020
E) Wednesday, May 13, 2020
Correct Answer:

Verified
Correct Answer:
Verified