Multiple Choice
Most of the scheduling methods available today require the project manager to classify the project as either _______ constrained or ______ constrained.
A) time, quality
B) quality, resource
C) cost, time
D) quality, cost
E) time, resource
Correct Answer:

Verified
Correct Answer:
Verified