Multiple Choice
If three copiers are needed to produce a final report on time and only two are available, the project is facing a(n) ________ type of resource constraint.
A) physical
B) people
C) material
D) equipment
E) budget
Correct Answer:

Verified
Correct Answer:
Verified
Q81: Resource dependency takes priority over technological dependency
Q82: Most of the scheduling methods available today
Q83: Which constraint category should be considered before
Q84: When deciding which staff to team-up to
Q85: Having individual staff members assigned to multiple
Q87: The level of resources each activity will
Q88: A project leader has realized that two
Q89: Consider the following table of activities A
Q90: Resource dependency takes priority over the technological
Q91: The inability to fit more than two