Multiple Choice
Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume the project starts on Monday, May 4, 2020 and no work is done on weekends (Saturday and Sunday) .
A) Monday, May 18, 2020
B) Tuesday, May 19, 2020
C) Friday, May 22, 2020
D) Tuesday, May 26, 2020
E) Monday, May 25, 2020
Correct Answer:

Verified
Correct Answer:
Verified