Multiple Choice
Consider the following table of activities A through E in which A is the start node and E is the stop node. Assume the project starts on Monday, May 4, 2020 and no work is done on weekends (Saturday and Sunday) . All activities require the same resource. Assume no working-day holidays during the months of May and June-no Memorial Day holiday, for example.
A) Monday, June 8, 2020
B) Wednesday, June 10, 2020
C) Friday, June 5, 2020
D) Thursday, June 11, 2020
E) Thursday, June 4, 2020
Correct Answer:

Verified
Correct Answer:
Verified
Q66: In a resource-constrained project, the first, or
Q67: When using the _ scheduling technique, startup
Q68: A shortage of software developers to create
Q69: In a resource-constrained project, the completion date
Q70: Scheduling projects classified as resource-constrained focuses on
Q72: Why is a schedule not a schedule
Q73: A project cost baseline is also called
Q74: Without a time-phased budget a good project
Q75: Consider the following table of activities A
Q76: A lack of readily available engineers is