Multiple Choice
_____________ is a measure of how easy it would be to notice that a risk event was going to occur in time to take mitigating action, that is, how much warning you would have.
A) Detection difficulty
B) Impact scaling
C) Probability analysis
D) Awareness level
E) Warning assessment
Correct Answer:

Verified
Correct Answer:
Verified