Multiple Choice
One of the choices below refers to major unforeseen risks and endeavors to supply funds for the same. Which choice is it?
A) Project reserves
B) Management reserves
C) Time buffers
D) Activity reserves
E) Contingency reserves
Correct Answer:

Verified