________ Reserves Are Identified for Specific Work Packages and Are

Question 20

Multiple Choice

________ reserves are identified for specific work packages and are distributed by the project manager and the team members.


A) Incremental
B) Contingency
C) Additional
D) Work package
E) Incidental

Correct Answer: