Multiple Choice
The implications of an identified change need to be assessed by
A) the primary project stakeholder.
B) the chief fiscal officer.
C) a person with expertise related to the change.
D) the authorizing project manager.
E) the program manager.
Correct Answer:

Verified
Correct Answer:
Verified