Multiple Choice
When considering risk response development, changing the plan to eliminate the risk or condition is known as ____________ the risk.
A) transferring
B) escalating
C) avoiding
D) retaining
E) diminishing
Correct Answer:

Verified
Correct Answer:
Verified