An uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives is known as a __________.
A) milestone
B) risk
C) happening
D) instant in time
E) event whose probability of occurrence is unknown
Correct Answer:

Verified
Correct Answer:
Verified