A ____________ Is an Alternative That Will Be Used If

Question 36

Multiple Choice

A ____________ is an alternative that will be used if a possible foreseen risk event becomes a reality.


A) management plan
B) risk management plan
C) contingency plan
D) alternative plan
E) alternative risk plan

Correct Answer: