menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Study Set 3
  4. Exam
    Exam 6: Developing a Project Schedule
  5. Question
    An Activity That Has More Than One Dependency Arrow Flowing
Solved

An Activity That Has More Than One Dependency Arrow Flowing

Question 107

Question 107

Multiple Choice

An activity that has more than one dependency arrow flowing into it is termed a(n)


A) parallel activity.
B) critical path.
C) burst activity.
D) merge activity.
E) independent activity.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q102: When translated into a project network, a

Q103: When completing a forward pass, you carry

Q104: Consider the following table of activities A

Q105: Only activities that occur at the end

Q106: The requirement for a freshly poured foundation

Q108: _ activities are to be completed immediately

Q109: The longest path through a project network

Q110: When completing the forward pass, the project

Q111: What is a Gantt chart and what

Q112: Consider the following table of activities A

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines