menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Study Set 3
  4. Exam
    Exam 6: Developing a Project Schedule
  5. Question
    The Longest Path Through a Project Network Is Called the _________
Solved

The Longest Path Through a Project Network Is Called the _________

Question 109

Question 109

Multiple Choice

The longest path through a project network is called the _________.


A) project duration
B) complete path
C) calculated total path
D) analytical path
E) critical path

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q104: Consider the following table of activities A

Q105: Only activities that occur at the end

Q106: The requirement for a freshly poured foundation

Q107: An activity that has more than one

Q108: _ activities are to be completed immediately

Q110: When completing the forward pass, the project

Q111: What is a Gantt chart and what

Q112: Consider the following table of activities A

Q113: Which of the following is true about

Q114: In developing a project network, neither looping

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines