menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Study Set 3
  4. Exam
    Exam 6: Developing a Project Schedule
  5. Question
    ________ Activities Must Be Completed Immediately Before a Particular Activity
Solved

________ Activities Must Be Completed Immediately Before a Particular Activity

Question 42

Question 42

Multiple Choice

________ activities must be completed immediately before a particular activity.


A) Merge
B) Burst
C) Predecessor
D) Successor
E) Parallel

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q37: An activity is an element of the

Q38: An element in the project that consumes

Q39: An activity cannot begin until ALL preceding

Q40: Consider the following table of activities A

Q41: A _ activity is one that has

Q43: If a project has more than one

Q44: Determine the critical path, total slacks for

Q45: A sequence of connected, dependent activities is

Q46: A merge activity is one that merges

Q47: Consider the following table of activities A

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines