If a Project Has More Than One Activity That Can

Question 43

Multiple Choice

If a project has more than one activity that can begin when the project is to start, a common start node should be used to indicate a clear project beginning on the network. Without a common start node, each path is a


A) critical path.
B) parallel path.
C) dangler path.
D) multiple start path.
E) confused path.