Multiple Choice
When completing a backward pass, you carry the LS to the next preceding activity to establish the LF, unless the next preceding activity is a burst activity, in which case you select
A) the smallest LS of all its immediate successor activities to establish the LF.
B) the largest ES of all its immediate successor activities to establish the LF.
C) the average LS of all its immediate successor activities to establish the LF.
D) the smallest ES of all its immediate successor activities to establish the LF.
E) the largest LS of all its immediate successor activities to establish the LF.
Correct Answer:

Verified
Correct Answer:
Verified
Q79: The forward pass in project network calculations
Q80: A _ activity is one that has
Q81: What is a hammock activity and give
Q82: On a project network, the activity times
Q83: A(n) _ calculates how late an activity
Q85: On a piece of scratch paper, draw
Q86: In a project network, _ indicate activity
Q87: Which of the following can be used
Q88: Which of the following is provided by
Q89: Consider the following table of activities A