Multiple Choice
Consider the following table of activities A through G in which A is the start node and G is the stop node.
A) Non-critical activity
B) Critical activity
C) Merge activity
D) Burst activity
E) Both critical activity and merge activity
Correct Answer:

Verified
Correct Answer:
Verified