menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management Study Set 3
  4. Exam
    Exam 6: Developing a Project Schedule
  5. Question
    A Network Has Only One Critical Path and the Slack
Solved

A Network Has Only One Critical Path and the Slack

Question 70

Question 70

Multiple Choice

A network has only one critical path and the slack for noncritical activities is high. This network would appear to have a _______ level of sensitivity


A) moderate
B) high
C) extreme
D) low
E) very high

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q47: Consider the following table of activities A

Q65: For any activity that has one or

Q66: The backward pass through a project network

Q68: A project network provides the basis for<br>A)

Q69: The activity time estimates used to build

Q71: The forward pass through a project network

Q72: Consider the following table of activities A

Q73: What is the difference between free slack

Q74: Consider the following table of activities A

Q75: Within an Activity-on-Node network, the arrows depict

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines