Multiple Choice
For any activity that has one or more predecessors, the ________ time is always the largest early finish of any of its predecessors. If the early finish times of an activity's predecessors were 85, 70 and 55, then this time would be the largest of these three early finish times or 85.
A) early finish
B) late finish
C) early start
D) late start
E) free slack
Correct Answer:

Verified
Correct Answer:
Verified