Multiple Choice
Refining estimates may be necessary for a number of reasons. For example, design flaws being revealed after the fact, extreme weather conditions, and accidents occurring are good examples of
A) hidden interaction costs.
B) things going wrong on a project.
C) changes in project scope.
D) normal conditions not applying.
E) uncertain, unstable requirements.
Correct Answer:

Verified
Correct Answer:
Verified