Multiple Choice
The estimating approach that is best to use on projects where there is an unusual amount of uncertainty surrounding the project and when it is impractical to estimate times and costs for the entire project is known as ___________.
A) range estimating
B) parametric procedure
C) template method
D) phase estimating method
E) WBS method
Correct Answer:

Verified
Correct Answer:
Verified