Multiple Choice
While it may be true that Mega Projects are by nature extremely difficult to estimate, another factor identified in the consistent pattern of estimating difficulties is:
A) unidentified risks.
B) deception.
C) economic downturn.
D) Both unidentified risks and economic downturn.
E) None of these alternatives is correct.