Benefits of Reference Class Forecasting include
A) acts as a reality check.
B) helps to avoid unsound optimism.
C) provides a basis for contingency funds.
D) leads to improved accountability.
E) All of these alternatives are correct.
Correct Answer:

Verified
Correct Answer:
Verified