The preferred method for situations involving strategic decision making, projects with a high degree of uncertainty, and projects with an unstable scope is the ___________ approach to estimating project time and costs.
A) top-down
B) experiential
C) bottom-up
D) reference class
E) professional estimation
Correct Answer: