Multiple Choice
The information necessary to conduct a bottom-up estimate of project time and cost starts with the ___________.
A) level 4 elements of the WBS
B) milestones
C) work package
D) planning horizon
E) level 5 elements of the PBS
Correct Answer:

Verified
Correct Answer:
Verified