Multiple Choice
The top-down method of estimating project time and costs that is useful for projects requiring the same task, group of tasks, or product repeated several times, especially if it is labor intensive, is the ______________.
A) ratio
B) consensus
C) apportion
D) function point
E) learning curves
Correct Answer:

Verified
Correct Answer:
Verified