Multiple Choice
The bottom-up method of estimating where work package time and costs for past projects are used as a starting point for a new project and adjustments are made based on differences in the new project is known as the ___________.
A) range estimating
B) parametric procedure
C) template method
D) phase estimating method
E) WBS method
Correct Answer:

Verified
Correct Answer:
Verified