The approach to estimating project time and cost that begins with an overall estimate for the project and then refines estimates for various stages of the project as it is implemented is known as ____________.
A) range estimating
B) parametric procedure
C) template method
D) phase estimating method
E) WBS method
Correct Answer:

Verified
Correct Answer:
Verified