Multiple Choice
A selective outline of the project that ensures the identification of all tasks and an understanding of what is to be done is called a(n) ____________.
A) process breakdown structure
B) work breakdown structure
C) organization breakdown structure
D) project breakdown structure
E) product breakdown structure
Correct Answer:

Verified
Correct Answer:
Verified