A Process Breakdown Structure can provide a reasonable alternative to a Work Breakdown structure for an extensive development project if
A) phase exit criteria are firmly established.
B) there are appropriate predecessor relationships in place.
C) deliverables are tightly aligned to milestones.
D) tangible products are being developed.
E) risk planning is included early in the project.
Correct Answer:

Verified
Correct Answer:
Verified