Multiple Choice
Scope creep results in changes to requirements, specifications, and priorities and these in turn result in _____ and _____.
A) added costs, budgetary overruns
B) project delays, schedule overruns
C) increases in scope, compromised requirements
D) cost overruns, delays
E) None of these alternatives is correct.
Correct Answer:

Verified
Correct Answer:
Verified