Multiple Choice
A project team that operates with a full-time project manager as a separate unit from the rest of the organization is structured using ________ organization.
A) functional
B) balanced matrix
C) weak matrix
D) strong matrix
E) projectized
Correct Answer:

Verified
Correct Answer:
Verified