Multiple Choice
Three possible outcomes emanate from each gate. They are ____.
A) continue, kill, enhance
B) reduce scope, kill, increase scope
C) proceed, cancel, or revise and submit
D) encourage, discourage, pass
E) allocate resources, reduce resources, cancel
Correct Answer:

Verified
Correct Answer:
Verified