Multiple Choice
If a preliminary proposal is approved, then ____.
A) the project is funded and execution begins
B) a project manager and staff are assigned to develop a more comprehensive implementation plan
C) the project is funded and formal detailed planning begins
D) the project is funded or shelved awaiting funding
E) the project is allocated limited resources
Correct Answer:

Verified
Correct Answer:
Verified
Q50: A proposed project that ranks high on
Q51: When considering criteria used to select projects,
Q52: The assessment of the internal and external
Q53: Typically, a project sponsor is<br>A) instrumental in
Q54: Three possible outcomes emanate from each gate.
Q56: In some cases, organizations will use a(n)
Q57: At each gate a(n) _ is made.<br>A)
Q58: The assessment of the external and internal
Q59: A list of potential projects, several criteria,
Q60: Strategy is implemented through projects.