Multiple Choice
Iterations are short time frames (time boxes) that typically last from __________.
A) 1-4 days
B) 1-2 weeks
C) 1-4 weeks
D) 4-7 weeks
E) 7-12 weeks
Correct Answer:

Verified
Correct Answer:
Verified