Multiple Choice
Which of the following is not one of the four value statements of the agile manifesto?
A) Individuals and interactions over processes and tools.
B) Working software over comprehensive documentation.
C) Customer collaboration over contract negotiation.
D) Established cost and duration over unpredictable cost and duration.
E) Responding to change over following a plan.
Correct Answer:

Verified
Correct Answer:
Verified