Scrum Relies on Three Key Roles

Question 44

Multiple Choice

Scrum relies on three key roles. A person who facilitates the Scrum process and resolves impediments at the team and organizational level is called a


A) scrum master.
B) project champion.
C) scrum leader.
D) product owner.
E) production coordinator.

Correct Answer: