Multiple Choice
Using Scrum methodology, specific features are created according to four distinct phases during each sprint. The third phase is to__________ the feature so that it is functional.
A) design
B) build
C) testing
D) delivery
E) analysis
Correct Answer:

Verified
Correct Answer:
Verified