Multiple Choice
Which of the following is NOT true of a development team using Scrum methodology?
A) The team is self-organizing.
B) They have the authority to change features and priorities at the end of each sprint.
C) The team is typically made up of 5 to 9 people.
D) They are responsible for achieving the commitments they make at the sprint planning and review meetings.
E) There are no designated roles or titles.
Correct Answer:

Verified
Correct Answer:
Verified
Q62: Identify and describe three principles found in
Q63: Scrum relies on three key roles. A
Q64: Specific features are created using Scrum methodology
Q65: In place of a product WBS, Scrum
Q66: While agile project management does not consist
Q68: Agile methods can be used on larger
Q69: While agile project management does not consist
Q70: Specific features are created using Scrum methodology
Q71: Freezing the design as late as possible
Q72: Short time frames (time boxes) that typically