Multiple Choice
Specific features are created using Scrum methodology according to four distinct phases. Which of the following places these phases in the correct order?
A) Design, Build, Analysis, Test
B) Monitor, Design, Build, Test
C) Analysis, Design, Build, Test
D) Design, Build, Monitor, Test
E) Analysis, Design, Build, Monitor
Correct Answer:

Verified
Correct Answer:
Verified
Q59: Project difficulty varies according to the extent
Q60: _represents the amount of work the team
Q61: In agile project management, projects evolve rather
Q62: Identify and describe three principles found in
Q63: Scrum relies on three key roles. A
Q65: In place of a product WBS, Scrum
Q66: While agile project management does not consist
Q67: Which of the following is NOT true
Q68: Agile methods can be used on larger
Q69: While agile project management does not consist