Multiple Choice
__________represents the amount of work the team commits to complete during the next sprint.
A) Sprint backlog
B) Product backlog
C) Project backlog
D) Schedule backlog
E) Task backlog
Correct Answer:

Verified
Correct Answer:
Verified