Multiple Choice
When a project starts with a high priority but it is canceled because its rank erodes or crashes during its project life cycle is an example of what type of project closure?
A) Normal
B) Premature
C) Perpetual
D) Failed project
E) Changed priority
Correct Answer:

Verified
Correct Answer:
Verified