Multiple Choice
Within which Maturity Model level are project audits performed on all significant projects and lessons learned are recorded and used on subsequent projects?
A) Ad Hoc Project Management
B) Formal Application of Project Management
C) Institutionalization of Project Management
D) Management of Project Management System
E) Optimization of Project Management System
Correct Answer:

Verified
Correct Answer:
Verified
Q16: In retrospective methodology, a facilitator uses _