A project that finishes within budget, on schedule and with full functionality goes through _____ closure, whereas a project whose technology did not work and got canceled goes through a _______ closure.


A) changed priority, premature
B) perpetual, normal
C) normal, premature
D) perpetual, changed priority
E) normal, failed project