Two views (perspectives) are collected when the audit questionnaires are collected and two sets of questions are used for each view. What are those two views?
A) Program manager view and the project manager view
B) Senior management view and customer view
C) Organization view and project team view
D) Customer view and project team view
E) Project manager and project team view
Correct Answer:

Verified
Correct Answer:
Verified