Baseline project budgets are derived from
A) the organization's overall budget.
B) time-phasing the work packages.
C) top management directions.
D) the total direct, direct project overhead and G&A overhead costs.
E) the earned value system.
Correct Answer:

Verified
Correct Answer:
Verified